First Article Inspection (FAI) is a planned and documented inspection process used to verify whether the first production item or a representative item from the initial production run meets the specified design, material, dimensional, functional, and other applicable requirements.
The purpose of FAI is not simply to check whether one product is acceptable. It is also to provide objective evidence that the manufacturing process, production documentation, tooling, and inspection methods can produce items that conform to the defined requirements.[1]
FAI is commonly used in industries where product specifications and manufacturing consistency require detailed verification. In aerospace and defense, AS9102 establishes specific requirements for performing and documenting FAI.[2]
A product may look correct while still differing from its approved drawings, specifications, or material requirements. If these differences are not identified before regular production continues, the same issue may be repeated across a larger quantity.
FAI helps manufacturers and buyers:
FAI provides evidence about the initial production process and representative product. It does not, by itself, guarantee that every subsequent unit will conform.
FAI is generally planned before or at the beginning of the first production run, using one or more items representative of the intended production process.
Typical situations in which FAI may be required include:
Whether a full or partial FAI is necessary after a change depends on the applicable standard, customer requirements, and the nature of the change. For example, Boeing's supplier guidance identifies engineering, process, and tooling changes as factors that may invalidate previous FAI results and require review.[3]
FAI requirements should therefore be agreed upon before production begins rather than assumed to apply identically to every order.
The inspection scope should be based on the product's approved requirements and the agreed FAI plan. Depending on the product, it may include:
| Inspection Area | Typical Verification |
|---|---|
| Dimensions | Length, width, height, thickness, diameter, tolerances, and other drawing dimensions |
| Materials | Material type, grade, composition, and supporting material certificates where required |
| Appearance and workmanship | Surface condition, finish, assembly quality, and visible defects |
| Functionality | Operation, fit, movement, performance, and other specified functional requirements |
| Components and construction | Component identification, assembly details, and conformity to the approved product structure |
| Special processes | Applicable finishing, coating, heat treatment, or other process records and test evidence |
Not every product requires every item in this table. The inspection scope should reflect the actual design characteristics, product specifications, and customer acceptance requirements.
A typical FAI process includes the following steps:
Collect and review the latest approved drawings, product specifications, purchase order, bill of materials (BOM), and applicable testing or inspection requirements.
Identify the product characteristics to be verified, the inspection methods, responsible personnel, measuring equipment, and required supporting records.
Use items produced through the intended manufacturing process. A prototype made using a different process may not provide representative evidence of normal production capability.[1]
Measure dimensions, examine materials and workmanship, and conduct functional or other specified tests. Record the actual results against the relevant requirements.
Compile the inspection results and supporting evidence into a First Article Inspection Report (FAIR), where required.
Document any nonconformities, agree on corrective actions, and determine whether another inspection or updated FAI record is necessary before proceeding.
A First Article Inspection Report (FAIR) is the documented record of an FAI. It presents the inspection results and supporting evidence used to demonstrate whether the inspected item meets the applicable requirements.
Depending on the applicable standard and customer requirements, a FAIR may contain:
For aerospace applications, AS9102 specifies a structured FAI documentation approach, including the use of defined report forms and supporting records.[2]
For other industries, the FAIR format and level of detail may vary according to the buyer's requirements and the product's complexity.
FAI and routine product inspections serve different purposes. FAI focuses on verifying the initial production item and the manufacturing process's ability to meet defined requirements. Other inspections may take place at different stages or use different sampling approaches.
| Inspection Type | Main Focus | Typical Timing |
|---|---|---|
| First Article Inspection (FAI) | Verify initial production conformity and manufacturing readiness | Before or at the beginning of the first production run |
| During Production Inspection (DUPRO) | Check product quality and workmanship while production is ongoing | During production |
| Pre-Shipment Inspection (PSI) | Assess finished goods against agreed requirements before shipment | After production is complete and goods are sufficiently packed |
FAI does not replace ongoing production monitoring or final inspection. A satisfactory first article is evidence about the inspected item and the process represented by it; continued quality control is still needed throughout production.
Not necessarily. Sample approval may confirm that a sample's appearance, design, or function is acceptable to the buyer. FAI is a more structured verification process that checks specified product characteristics and, depending on the applicable requirements, provides evidence that the intended production process can produce conforming items.
No. FAI may use one or more representative items from the first production run. The number of items and inspection scope depend on the applicable standard, product requirements, and customer agreement.[1]
No. FAI is not a universal requirement for all products or industries. It may be required by a customer, contract, industry standard, or internal quality procedure. AS9102 specifically addresses FAI requirements in the aerospace and defense supply chain.[2]
No. FAI verifies the inspected item and provides evidence about the production process represented by that item. It does not replace ongoing process control, in-process inspection, or final product acceptance.
[1] International Aerospace Quality Group (IAQG). 9102 First Article Inspection Requirement. https://iaqg.org/standard/9102-first-article-inspection-requirement/
[2] SAE International. AS9102C: Aerospace Series — First Article Inspection Requirements. Revised June 28, 2023. https://saemobilus.sae.org/standards/as9102c-aerospace-series-first-article-inspection-requirements
[3] The Boeing Company. First Article Inspection (FAI). Supplier quality guidance. https://www.boeingsuppliers.com/become/quality/fai